Which power generation unit in Karnataka set a national record in the commissioning of a power generation station in a record time of 25 months in the year 2016-17?
- (1)RTPS unit-7
- (2)BTPS unit-3
- (3)YTPS unit-1
- (4)None of the above
Correct answer
From the official answer key, including any revision.
- (1) RTPS unit-7
Explanation
Why this is the answer, and why the other options are not.