A certain number of men can complete a piece of work in 6k days, where k is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k days?
- (1)10%
- (2)(50/3)%
- (3)20%
- (4)25%
हिन्दी
एक निश्चित संख्यक व्यक्ति एक कार्य को 6k दिनों में पूरा कर सकते हैं, जहाँ k एक धनपूर्ण संख्या है। व्यक्तियों की संख्या में कितने प्रतिशत की वृद्धि की जाए ताकि यह कार्य 5k दिनों में पूरा किया जा सके?
- (1)10%
- (2)(50/3)%
- (3)20%
- (4)25%
Correct answer
From the official answer key, including any revision.
- (3) 20%