Skip to content
June 2021CSEQuestion 80 of 79

UPSC CSE Csat Paper 2 June 2021: question 80

Question

English

A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50% ?

  1. (1)24
  2. (2)21
  3. (3)18
  4. (4)15

हिन्दी

एक व्यक्ति किसी कार्य के 7/8 अंश को 21 दिन में पूरा करता है । यदि कार्य की मात्रा में 50% की और वृद्धि हो जाए, तो उसे उस कार्य को समाप्त करने में कितने दिन और लगेंगे ?

  1. (1)24
  2. (2)21
  3. (3)18
  4. (4)15

Correct answer

From the official answer key, including any revision.

  • (4) 15

Explanation

Why this is the answer, and why the other options are not.

The explanation for this question is available free with an account, together with the explanation for every other question you attempt.

Topic

More previous year questions on the same subject, topic and sub-topic.

  1. subject: Aptitude and Reasoning
  2. topic: Quantitative Aptitude
  3. sub-topic: Time and Work