A person X can complete 20% of work in 8 days and another person Y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?

  1. (1)6
  2. (2)8
  3. (3)10
  4. (4)12

हिन्दी

एक व्यक्ति X किसी कार्य का 20%, 8 दिनों में पूरा कर सकता है और दूसरा व्यक्ति Y उसी कार्य का 25%, 6 दिनों में पूरा कर सकता है। यदि वे दोनों साथ-साथ काम करते हैं, तो उस कार्य का 40% कितने दिनों में पूरा हो जाएगा?

  1. (1)6
  2. (2)8
  3. (3)10
  4. (4)12

Correct answer

From the official answer key, including any revision.

  • (1) 6

Explanation

Why this is the answer, and why the other options are not.

The explanation for this question is available free with an account, together with the explanation for every other question you attempt.

Topic

More previous year questions on the same subject, topic and sub-topic.

  1. subject: Aptitude and Reasoning
  2. topic: Quantitative Aptitude
  3. sub-topic: Time and Work